RT Infrastructure Solutions is pleased to announce the successful test and commissioning of signalling works at Shipley, Guiseley, Menston and Burnley-in-Wharfdale stations in conjunction with Network Rail’s Leeds North West Platform Extension Project. After utilising multiple weekend ROTR possessions to undertake as much signalling enabling & signalling installation prep-works as possible, all stations were commissioned on time, defect-free, over back-to-back weekends in April.

The newly commissioned works will allow the stations to bring into service new platform lengths able to accommodate longer, 6-car (2×3-car) Class 331 trains.

As part of the works package, RT Infrastructure Solutions was also responsible for the installation of 2 new IBJ’s at both Shipley and Menston Stations. These were seamlessly installed and handed back under Network Rail’s Pway standards.

RT Infrastructure Solutions undertook all of the ES 6-8 works in conjunction with the four stations that included the following deliverables :

  • Provision of Signalling Project Management
  • Provision of Signalling CRE and Pway CRE
  • Provision of Tester-In-Charge and Testing Management
  • Production of Testing & Commissioning Documentation
  • Signalling and Pway Surveys
  • SMTH cover for civils works
  • Signalling Enabling works
  • Installation of new IBJS
  • Installation of new track circuit equipment for altered length track circuits
  • Recovery of existing IBJs
  • Installation of new AWS & TPWS equipment
  • Installation of new Off Indicators
  • Installation of New Signalling Signage
  • Installation of all new signalling cables
  • Prep-Testing of new equipment by Signal Works Testing Personnel
  • Testing of C-Asdo Beacons.
  • Scheme Plan Verification
  • Signalling Test & Commissioning
  • Removal and recoveries of redundant signalling equipment.
  • Renewal of life expired equipment.