Bardon Level Crossing is a public highways manned barrier situated at 111 miles and 22 chains on the Midland and Continental Route.

Bardon Level Crossing is a public highways manned barrier situated at 111 miles and 22 chains on the Midland and Continental Route. With over 2,800 vehicles using the crossing daily, it has a collective risk rating of 6.

The crossing is predominately used by freight trains and runs to a quarry owned by Aggregate Industries. Due to this arrangement – and because the crossing spans the busy A511 – an upgrade was required to improve efficiency and safety.

The ORR proposed that the existing crossing was to be renewed with the provision of a full barrier solution to seal off the railway corridor to pedestrians and traffic whilst trains were crossing. The crossing was upgraded to a traincrew operated barrier crossing with auto raise provision, driver’s white lights and two new locally-controlled units.

Working from signalling design produced by TSP, RT-IS managed all the Network Rail GRIP 6-8 processes. This work included the management and procurement of all level crossing equipment and materials. Site installation works were undertaken by our IRSE-licensed personnel, including all pre-testing and the commissioning into service of the new system.

Over 2,000 site-hours were reached as part of the works with zero incidents, and the project was delivered on time and to budget.

Activities Undertaken

  • Production of all signalling documentation for lineside activities
  • Production of T&C strategy and T&C plans
  • Factory build and test of new location cases
  • Signalling correlation of existing assets / Undertaking of temporary enabling works
  • Installation of train detection equipment and auto-rise facility
  • Sighting and installation of drivers indications, RTL’s and railway signage
  • Design and implementation of test simulator
  • Supply and installation of two local control units and all LX pedestals and booms
  • Installation and termination of all lineside cables
  • Supply, Installation and E&P Commissioning of new FSP
  • Controlled changeover and testing including full Principles testing
  • All pre-testing and commissioning to Network Rail standard NR-L2-SIG-30014

client

Alma Rail

Project value

£345,000

duration

October 2018 — August 2019