This £6m scheme to undertake modifications to Fratton Depot saw RTIS deliver all signalling requirements on behalf of Buckingham Group.
This £6m scheme to undertake modifications to Fratton Depot saw RTIS deliver all signalling requirements on behalf of Buckingham Group.
Our Signalling Project Engineers and CREs oversaw this complete process, liaising with signalling designers to complete all the GRIP 6-8 activities including the procurement and management of all new signalling assets and multi-core cabling.
Final entry into service for the scheme was achieved in October 2020, with zero test logs raised. RTIS comprehensively delivered all works on time, within budget and with zero accidents/incidents logged throughout the scheme.
Activities Undertaken
Cable running works (Multi-core signalling & power) & Cable diversion works
Re-location of split banner signal
Sighting and moving of multiple AZLM Axle Counters
Re-location of existing signals & new double OFF Indicators / Stop Car Markers
Mechanical Alterations in Norton Junction Signal Box
New diagram overlay at Norton Junction
Management of electronic and Train Describers alterations at WMSC
Installation of level crossing pedestals, barriers & RTL’s
Termination of Signalling Plug and Plug cables
client
Buckingham Group
Project value
£105,000
duration
December 2019 – November 2020